Courthouse Change Order 6

By John Bury | November 7, 2016

Yes, another one:

11/2/2016: Change Order 6:

$150,000 – 1/4/17

Bringing it to:
courtcost
To be added to these:

7/1/13: Construction Agreement APS Contracting, Inc.

$33,380,000 – 12/19/14

7/2/14: Change Order 1

$0.00 – 5/20/15

12/3/14: Change Order 2

$1,960,165.50 – 7/31/15

7/8/15: Takeover Agreement

5/4/16: Change Order 3

$358,882.83 – 1/4/17

6/8/16: Change Order 4

$158,533.03 – 1/4/17

9/7/16: Change Order 5

$990,000.03 – 1/4/17